Ottawa's new main library $131M over budget with city on hook for half

The design of the new library was unveiled in April of this year. And in August, the new name was revealed: Ādisōke, an Anishinaabemowin phrase that means storytelling. (Alexander Behne/CBC - image credit)
The design of the new library was unveiled in April of this year. And in August, the new name was revealed: Ādisōke, an Anishinaabemowin phrase that means storytelling. (Alexander Behne/CBC - image credit)

The price tag for Ottawa's new central library has shot up $131 million — an increase of almost 75 per cent — to $306 million, leaving the city on the hook for an additional $65 million, according to a report released Thursday.

Known as Ādisōke, an Anishinaabemowin phrase that means storytelling, the new super library is a joint project between the Ottawa Public Library and the federal Library and Archives Canada (LAC), with the cost split about 60-40 respectively.

The building will stand — some excavation and soil remediation has already begun — on Albert Street at the east end of LeBreton Flats.

The cost for the project was supposed to be fixed at $175 million with the federal government paying $71 million. The city would then pick up the remaining $104 million, plus an additional $18 million for the 200-spot underground garage.

When the two short-listed bidders sent in their proposals last month, each was way over-budget. PCL Construction had the lowest bid at $334 million: $306 million for the library and an additional $28 million for the garage, which has increased in price by $10 million.

The city's portion of the project has now increased by $64 million to $168 million. And, according to the report, an additional $1.2 million will be required to fit up the food and beverage operations in the new library.

That means the city has to find more than $65 million to keep the project alive, a problem it will discuss at a special finance and economic development committee meeting on Oct. 19.

Alexander Behne/CBC
Alexander Behne/CBC

The Treasury Board has already approved the increased costs for the federal part of the project.

City staff recommends the city borrow an additional $36 million because the extra debt falls within council's self-imposed ceiling of 7.5 per cent of tax revenue going toward debt servicing.

The library would contribute $28 million: $16 million would come from the library's own surplus fund (it's saved millions over the last 18 months due to COVID-19 restrictions) and $12 million would come from a development charge fund that pays for expanding public libraries.

The city would also borrow an additional $10 million to pay for the overrun costs for the parking garage. The underground garage is to be paid for by parking fees. The additional $10 million for the parking garage is not included in the total increase.

The completion date has also been put off by another year — again. The original completion date was in 2023 but that has now shifted to 2026, assuming council approves the extra money for the project.

Construction inflation to blame: report

The report blames the giant jump in the project's budget on soaring construction costs.

In 2016, when it estimated the cost of the library, the city's procurement staff included a 10 per cent "escalation contingency," but that has now ballooned by 55 percentage points, according to the report.

"Actual observed construction inflation in Ottawa, as outlined by Statistics Canada to mid-point construction, is currently in excess of 65 per cent, which has been confirmed by a third-party quantity surveyor," the report said.

The report goes on to say COVID-19 is increasing costs due to material shortages, pressures on the supply chain, impacts on labour and "a superheated market."