What’s happened since the bridge collapsed at FIU, killing six? Here’s a timeline

At 1:47 p.m. on March 15, 2018, the 950-ton bridge conceived by Florida International University to cross eight lanes of Southwest Eighth Street in front of its flagship campus collapsed.

Here are some key markers leading up to that catastrophe, which caused the deaths of six people, and what has happened since:

READ MORE: Cautious new bridge design almost ready

READ MORE: Repercussions on key players in failed bridge that fell in 2018

March 10, 2018 After assembling the bridge’s main 174-foot, steel-and-concrete span by the side of Southwest Eighth Street and 109th Avenue while support towers were built at either end, construction crews hoist the span and lower it into place by special gantry cranes at about 2 a.m.

An early morning view of the main span of the FIU-Sweetwater pedestrian bridge as it was hoisted from its temporary supports, rotated 90 degrees and placed across Southwest Eighth Street at 109th Avenue, Saturday, March 10, 2018. Five days later, on March 15, 2018, the 174-foot, 950-ton bridge span collapsed, killing six people.
An early morning view of the main span of the FIU-Sweetwater pedestrian bridge as it was hoisted from its temporary supports, rotated 90 degrees and placed across Southwest Eighth Street at 109th Avenue, Saturday, March 10, 2018. Five days later, on March 15, 2018, the 174-foot, 950-ton bridge span collapsed, killing six people.

March 15, 2018 — The bridge’s 950-ton span abruptly collapses, crushing cars stopped at a red light on Tamiami Trail and 109th Avenue at 1:47 p.m. that Thursday. Six people die: Alberto Arias, 53; Brandon Brownfield, 39; FIU student Alexa Duran, 18; Rolando Fraga, 60, and his partner Oswaldo Gonzalez, 57; and construction worker Navaro Brown, 37. Ten others are injured.

Six people died when the pedestrian bridge under construction connecting Florida International University and Sweetwater, across Southwest Eighth Street at 109th Avenue, collapsed on March 15, 2018.
Six people died when the pedestrian bridge under construction connecting Florida International University and Sweetwater, across Southwest Eighth Street at 109th Avenue, collapsed on March 15, 2018.

READ MORE: Who are the victims of the FIU bridge collapse now honored on campus?

Sept. 18, 2018 The Occupational Safety and Health Administration, a federal agency in charge of workers’ safety, cites five companies involved in the bridge: FIGG Bridge Engineers, Network Engineering Services, Structural Technologies, Munilla Construction Management and the Structural Group of South Florida. OSHA levied seven violations and said the companies failed to protect workers, did not provide them with a proper safety line and did not remove them from the area despite the bridge developing cracks of “significant width, depth and length at critical locations.” The agency proposes $86,658 in penalties.

Two days before the bridge collapsed on March 15, 2018, this photo showed a crack along the bottom of diagonal support No. 11.
Two days before the bridge collapsed on March 15, 2018, this photo showed a crack along the bottom of diagonal support No. 11.

Nov. 15, 2018 — Federal investigators from the National Transportation Safety Board issue a two-page report that concludes design flaws led to cracking in the southern portion in the bridge before it collapsed.

On March 16, 2018, National Transportation Safety Board inspectors stand along a section of the FIU bridge at Southwest Eighth Street and 109th Avenue. The bridge collapsed the day before, on March 15, killing six people.
On March 16, 2018, National Transportation Safety Board inspectors stand along a section of the FIU bridge at Southwest Eighth Street and 109th Avenue. The bridge collapsed the day before, on March 15, killing six people.

March 1, 2019 MCM, the contractor behind the collapsed bridge, files for bankruptcy protection.

June 3, 2019 Florida Department of Transportation releases documents showing that on the morning of the collapse, the firm that designed the span, FIGG, assured a meeting of state highway officials, university administrators, contractors and others that the bridge was safe.

June 11, 2019 — OSHA investigators issue a 115-page report that faulted all parties involved with the bridge, including FIU, state transportation officials and private contractors. This OSHA report is the first time federal investigators state unequivocally that Southwest Eighth Street should have been closed in response to the cracking on the bridge.

July 30, 2019 — The victims and their survivors reach a $102.7 million settlement, which a judge affirms on Dec. 12, 2019.

Sept. 20, 2019 — Will Watts, the chief engineer for the Florida Department of Transportation, sends a letter to the NTSB saying that FIU and its contractor were responsible for asking the state to close Tamiami Trail — but never did.

Nov. 13, 2019 The NTSB issues its final report, citing failures in design, lack of adequate oversight and systematic negligence as reasons for the fatal collapse. “All parties involved in the ... project to build the pedestrian bridge were aware of the cracks and their progression, including FDOT, FIU, FIGG (FIGG Bridge Engineers, who designed it), MCM (the bridge contractor, Munilla Construction Management), and Bolton, Perez (Bolton Perez and Associates, consulting firm that was supposed to act as a backstop on design and construction),” NTSB said in its 152-page report.

Feb. 26, 2021 — Nearly three years after the bridge collapse, FIU transfers $9.1 million to FDOT to build a new pedestrian bridge.

March 15, 2022 — FIU unveils a memorial on campus honoring Alexa Duran, the FIU student killed in the collapse: a 7-foot bronze sculpture of her, with five lamp posts surrounding it, to represent the other victims.

Alexa Duran, the 18-year-old Florida International University student killed in the collapse of the Florida International University bridge, on March 15, 2018. She was in a car sitting at a red light.
Alexa Duran, the 18-year-old Florida International University student killed in the collapse of the Florida International University bridge, on March 15, 2018. She was in a car sitting at a red light.
Gina and Orlando Duran, the parents of Alexa Duran, embrace during the unveiling of a memorial at Florida International University in Miami on the fourth anniversary of the FIU bridge collapse on Tuesday, March 15, 2022. The bronze sculpture of her is surrounded by five lamp posts to represent the five other people who died in the bridge collapse.
Gina and Orlando Duran, the parents of Alexa Duran, embrace during the unveiling of a memorial at Florida International University in Miami on the fourth anniversary of the FIU bridge collapse on Tuesday, March 15, 2022. The bronze sculpture of her is surrounded by five lamp posts to represent the five other people who died in the bridge collapse.

May 4, 2022 — FDOT engineers hold the first of two community town hall meetings in Sweetwater to share the new bridge design, a standard steel structure without the novel design of the first bridge.

May 2023 — FDOT expects to start the construction bidding for the new bridge.

2025 — New pedestrian bridge expected to be finished.