This huge renewable energy park will be as big as Singapore and visible from space
India is building what will likely be the world's largest renewable energy project.
Rising from the bare expanse of the large salt desert that separates the country from Pakistan, the solar and wind farm is expected to be completed three years from now.
The Khavda renewable energy park - named after the village nearest to the project site - will be so big that it will be visible from space, according to developers.
When completed, the project will be about as large as Singapore, spreading out over 726 square kilometres. The Indian government estimates it will cost at least $2.26 billion (€2.08b).
Shifting to renewable energy is a key issue at the ongoing COP28 climate summit. Some leaders have voiced support for a target of tripling renewable energy worldwide in any final agreement while curbing use of coal, oil and natural gas, which spew planet-warming gases into the atmosphere.
The park will power nearly 18 million homes
Once completed, the park will supply 30 gigawatts of renewable energy annually, enough to power nearly 18 million Indian homes.
India - the world’s most populous country - aims to install 500 gigawatts of clean energy by the end of the decade and to reach net zero emissions by 2070. This project site will likely contribute significantly to its transition to producing energy from non-carbon spewing sources.
As things stand, India is still mostly powered by fossil fuels, especially coal, which generate more than 70 per cent of its electricity. Renewable energy currently contributes about 10 per cent of India’s electricity needs. The country is also currently the third-largest emitter of planet-warming gases behind China and the United States.
India's renewable energy park is a short drive from the Pakistan border
At the park's site, thousands of labourers are installing pillars on which solar panels will be mounted. The pillars rise like perfectly aligned concrete cactuses that stretch as far as the eye can see.
Other workers are building foundations for enormous wind turbines to be installed. They also are transporting construction material, building substations and laying wires for kilometres.
What makes this heavy industrial activity peculiar is that it's taking place in the middle of the Rann of Kutch in western India’s Gujarat state.
The Rann is an unforgiving salt desert and marshland at least 70 kilometres from the nearest human habitation but just a short army truck ride away from one of the world’s most tense international borders separating India and Pakistan.
‘A bright future for the plant’: Giant solar space farm could be orbiting Earth by 2035
Arizona is building the first solar canal in the US. What are they and how do they work?
Workers face tough conditions building the Khavda renewable energy park
An estimated 4,000 workers and 500 engineers have been living in makeshift camps for the better part of the past year toiling to get this project up and running.
They face tough conditions: in September, unseasonal heavy rains left the ground muddy and water logged since the only escape for water in this rough terrain is evaporation.
This made it even harder for the workers to do their job.
“There are people working here from all over India,” says KSRK Verma, Khavda project head for Adani Green Energy Limited, the renewable energy arm of the Adani Group, which the Indian government has contracted to build 20 gigawatts of the project.
Verma, with over 35 years of experience building dams across turbulent South Asian rivers and enormous natural gas tanks under the Bay of Bengal, says this is one of the most difficult projects he’s undertaken.
“It’s not at all [an] easy site to work at, there is no habitation, the land is marshy, there are a lot of high winds, rains and this is a high earthquake prone area,” says Vneet Jaain, managing director of Adani Green at its headquarters in the city of Ahmedabad.
Jaain who has overseen multiple ambitious projects for the Adani Group says the first six months were spent just building basic infrastructure. “From April this year is when we started working on the actual project,” he adds.
The Adani Group has been in the limelight this year ever since the US-based short-selling Hindenburg Research firm accused the group and its head, Gautam Adani, of “brazen stock manipulation” and “accounting fraud”. Adani Group has called the allegations baseless.
Jaain of Adani Green says the allegations have had little impact on its ongoing projects including work at the Khavda renewable energy park.
India has come 'a long way' in its renewable energy drive
“Twenty years ago, India was exactly where a vast expanse of [the] developing world was,” Ajay Mathur, director general of the International Solar Alliance, says of the country's renewable energy production. The alliance has 120 member countries and promotes renewable energy - primarily solar - across the world.
About 200 kilometres away in the industrial city of Mundra, also located along the Gujarat state’s coastline, the Adani Group is manufacturing the solar and wind energy parts needed for the project. It's one of the few locations in India where most solar energy components are made from scratch.
Some of the factories are run like laboratories, with protective gear, face masks and head covers required to avoid dust particles that can compromise solar cells.
The nearby wind energy factory aims to produce 300 turbines a year, with each blade stretching nearly 79 metres and weighing 22 tonnes. Each wind turbine generator is capable of producing 5.2 megawatts of clean energy. They will be India’s biggest.
As Mathur of the solar alliance says, “India has traveled a long way”, and its large-scale renewable energy projects including the Khavda park will be inspiring for other developing countries. “Here is a country that was exactly where they are today and was able to make the change,” he says.
Activists criticise lack of environmental impact assessments
While acknowledging the importance of transitioning to renewable energy, environmental experts and social activists say India’s decision to allow clean energy projects without any environmental impact assessments is bound to have adverse consequences.
“The salt desert is a unique landscape” that is “rich in flora and fauna”, including flamingos, desert foxes and migratory bird species that fly from Europe and Africa to winter in this region, according to Abi T Vanak, a conservation scientist with the Bengaluru-based Ashoka Trust for Research in Ecology and the Environment. Vanak has overseen multiple environment-related research projects in the Kutch region.
Kutch and other similar regions are classified as “wastelands” by the Indian government - and Vanak says this is extremely unfortunate. “They are not recognised as valid ecosystems,” he says.
‘A national priority’: Greece is powering ahead with plans for first offshore wind farms
Bubble curtains are being used to protect marine life from noisy wind farm construction
With renewable energy projects exempt from environmental impact assessments, “There is no system in place” to determine the best places for them, according to Sandip Virmani, an environmentalist based in Kutch.
At a little over 45,000 square kilometres, the Kutch district is as big as Denmark and is India’s largest district. Given this, Virmani says there is enough land in Kutch for various renewable energy projects. But he fears that dairies and other local businesses in the region might be impacted by large-scale projects. “It has to be in the context of not compromising on another economy,” he says.
Meanwhile, longtime residents are still waiting to see how this huge project near their village will affect them.
Hirelal Rajde, 75, who has spent most of his life in Khavda, is mindful of the upcoming energy project as well as the increase in tourism in recent years in this otherwise desolate region. “I think these developments are both good and bad,” says Rajde.
“I think overall though it will benefit more than it will cause problems," he says. "I tell everyone who lives here to hold onto their land, don’t sell it. In a few years, I tell them they’ll have so much business that they won’t be able to rest even at night.”