OSEG defends Lansdowne 2.0, as committee defers vote

Members of the finance and planning committees opted not to vote on any of the proposed motions to adjust the latest Lansdowne 2.0 proposal and will instead debate them at a special council meeting next Friday. (City of Ottawa - image credit)
Members of the finance and planning committees opted not to vote on any of the proposed motions to adjust the latest Lansdowne 2.0 proposal and will instead debate them at a special council meeting next Friday. (City of Ottawa - image credit)

Ottawa city councillors are no closer to providing a decision on a contentious $419-million deal to redevelop Lansdowne Park, ending two days of 10-hour discussions without a vote.

More than 80 people gave delegations about their concerns or support for the project, which would see two residential towers erected next to a newly rebuilt north-side stands and an event centre added east of the stadium.

The public-private partnership with Ottawa Sports and Entertainment Group (OSEG) has only ever operated at a loss.

But OSEG executives bristled at suggestions that it's been a failure.

"I kind of cringe a little bit every time I hear that the city has lost a lot of money," said Roger Greenberg, OSEG executive chairman. "Everything that the city put in, they're getting back."

Greenberg said the city did not get any profits from the complicated financial system known as the waterfall, but it gained by no longer having to foot the bill for its 60s-era infrastructure.

"The city is no worse off, in fact much better off, for at least having a new south-side stands and parking and has saved all that other money... I think it's been a tremendous success from the city's perspective. It hasn't been a great success from our perspective."

Managing partner of Ottawa Sports and Entertainment Group (OSEG) Roger Greenberg (left), executive director of OSEG Foundation Janice Barressi (centre) and OSEG CEO Mark Goudie (right) at the first day of Lansdowne 2.0 delegations on Nov. 2, 2023.
Managing partner of Ottawa Sports and Entertainment Group (OSEG) Roger Greenberg (left), executive director of OSEG Foundation Janice Barressi (centre) and OSEG CEO Mark Goudie (right) at the first day of Lansdowne 2.0 delegations on Nov. 2, 2023.

Managing partner of Ottawa Sports and Entertainment Group (OSEG) Roger Greenberg (left), executive director of OSEG Foundation Janice Barressi (centre) and OSEG CEO Mark Goudie (right) spoke to councillors at the two-day committee meeting. (Francis Ferland/CBC News)

That relationship is at the heart of the new proposal, which staff prepared with an eye for evening out the risk between the partners and ensuring financial sustainability.

The deal on the table predicts a healthy return over the course of the decades-long agreement, but also a $5-million per year investment of tax dollars for debt servicing, along with hundreds of thousands of dollars pulled separately from parking reserves.

Week's break to allow for compromise

Councillors came into the meeting Thursday morning with a goal of hearing from the public, gaining insight from staff and then coming to an agreement on the best way forward.

But at around 2:30 p.m. Friday after the final delegation had logged off, Mayor Mark Sutcliffe proposed to shelve any decisions until next Friday's special council meeting.

Many feared their exhaustion might limit meaningful debate. They suggested a few days to digest the dozens of motions to adjust the deal could inspire behind-the-scenes collaboration.

Capital ward Coun. Shawn Menard checks something on his computer during a committee meeting on Nov. 3, 2023.
Capital ward Coun. Shawn Menard checks something on his computer during a committee meeting on Nov. 3, 2023.

Capital ward Coun. Shawn Menard says the responses to his concerns were not enough to allay them. (Francis Ferland/CBC)

But Coun. Shawn Menard, who represents the ward where Lansdowne Park is located, worried it may cut discussions short.

"Everyone will have ample time," assured Mayor Mark Sutcliffe, who said there will be the option to extend the council meeting to several days. "There'll be no effort to limit debate or discussion on this issue."

Councillors weigh options

The rest of the meeting saw councillors focus on some of the key sticking points of public delegations: fiscal priorities, transportation issues, the amount of on-site affordable housing and accessibility issues at the current facilities.

College ward Coun. Laine Johnson asked several rounds of questions about the viability of the plan and risks for the city.

"We are stewards and we have a fiduciary responsibility to look at the risk to the City of Ottawa. That is why we are here today," she said.

Johnson expressed concerns about a key shift in the city's arrangements with OSEG.

College ward Coun. Laine Johnson watches a public delegation during a committee meeting on Nov. 3, 2023.
College ward Coun. Laine Johnson watches a public delegation during a committee meeting on Nov. 3, 2023.

College ward Coun. Laine Johnson said it's up to councillors to ensure this deal is in the best interest of residents. (Francis Ferland/CBC)

Under the first redevelopment deal, OSEG was on the hook for cost overruns from construction — and ended up shelling out $160 million. In Lansdowne 2.0 that risk is transferred to the city.

"I spoke to OSEG about whether or not they'd like to have those cost overruns back," Johnson said. "They said no."

Some councillors, including Somerset's Ariel Troster, expressed discomfort with asking for any money from taxpayers for what can be described as a "want-to-have" rather than a "must-have."

"I just think it's quite immoral," said Troster, referring to residents who may never go to the site helping to pay for its rejuvenation rather than adding a heftier surcharge to ticket sales.

"What will the market bear? Well, the question is what should residents bear?"

Others struggled to understand complicated financial manoeuvres put forward.

That includes a plan to have a developer build the residential towers from the underground parking lots up, but agree to sell back the main-level retail — while still maintaining ownership of parts of the lobby, elevators, stairs and mechanical rooms.

Isabelle Jasmine, the city's deputy treasurer, later described that plan as the "simplified" version.

Somerset ward Coun. Ariel Troster watches an online delegation on Nov. 3, 2023.
Somerset ward Coun. Ariel Troster watches an online delegation on Nov. 3, 2023.

Balancing the need to improve transit services and address a shortage of affordable housing with the new debt associated with Lansdowne 2.0 is troubling, Somerset ward Coun. Ariel Troster said during the meeting. (Francis Ferland/CBC)

Menard said the day's revelations in no way reassured him of the deal's value.

"The large portion of debt that comes along with this in what we're facing right now as a city, is still is a huge concern," he said after the meeting. "And I think that will remain a concern for a number of councillors, regardless of the tweaks that might come through motions."

Motions could dramatically change deal

Yet, the motions up for discussion next Friday could change elements of the deal, resurrecting previously eliminated source elements and diverting more money from the sale of property rights to fund affordable housing projects.

Sean Moore, the city's director for the Lansdowne Park project, said the city had reasons for kiboshing the third residential tower — one of the motions that appears to have support from several councillors.

"Staff are not recommending it," he said.

Greenberg also had reservations with the flurry of proposed changes.

"With all due respect, it's not a question of one partner saying 'we're going to institute all these changes,'" Greenberg said. "There were a substantial number of concessions that we made to get to last year's report."

"We are pushed, in my view, very close to the line," he said.

The Lansdowne 2.0 project proposed by Ottawa Sports and Entertainment Group would see a new municipally owned arena constructed at the end zone of the football field, partly on the current park space, paid for in large part by the development of three towers above new northside stands.
The Lansdowne 2.0 project proposed by Ottawa Sports and Entertainment Group would see a new municipally owned arena constructed at the end zone of the football field, partly on the current park space, paid for in large part by the development of three towers above new northside stands.

Several elements of the deal first proposed by OSEG, including a third residential tower and a green roof on the event centre, could return to the plans if motions are adopted by council. (Ottawa Sports and Entertainment Group)

Staff assured councillors at several points that whatever decisions are made next week, there will be opportunities to alter the agreement.

Sutcliffe told reporters this decision has been a "long time coming" and councillors cannot put it off any longer.

"Most of the people who want to see us pause are actually people who don't want to see this project go ahead. They're using the idea of pausing as a proxy for stopping it from happening," he said, adding that postponing the plan postpones new housing.

"I don't think that's wise."